Week 21: Finish Carpentry & Interior Trim Prep

Posted in 1915 Bungalow Remodel by abodepdx on May 21, 2010

Dana of Guillory Construction spent a full day resetting the sills on the casements so that the cranks would better clear the sills. He also recased the medicine cabinet so that it looks more traditional and detailed electrical panel. Awesome!

cased electrical panel

med cab & window millwork redone

Pablo and Pancho of Aspen Painting, LLC put two coats of clear sealer on the interior doors and handrail. They sanded and caulked the porch, front steps and guardrails. Painting the porch floor and front steps will go quickly next week.

Pablo and Pancho also spent a couple days masking the entire basement and stairs in preparation for painting the woodwork. The whole basement–walls, ceiling, floors, doors and windows–is covered and wrapped and ready for trim paint.

office

family room

family room @ storage

wet bar, laundry & stairs

mudroom hall @ av room storage

stairs

Tune in next time for even more finish carpentry & interior trim painting!

One Response

Subscribe to comments with RSS.

  1. JL Woodworking said, on June 2, 2010 at 1:37 pm

    These photos are a good display of how much work goes into making the finish work in a room look nice. That’s really nice looking trim carpentry work around the windows and an excellent looking set of stairs.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.